Electric Power Systems · System Operation

Economic Load Dispatch & LFC

Solved Problems — Electric Power Systems

Dr. Mithun Mondal engineeringdevotion.com
Demonstrative Video
SECTION 01

Problem-1

\[\begin{aligned} &F_{1}=0.2 P_{1}^{2}+40 P_{1}+120 \text { Rs per hr } \\ &F_{2}=0.25 P_{2}^{2}+30 P_{2}+150 \text { Rs per hr } \end{aligned}\]
The fuel inputs per hour of plants 1 and 2 are given as
SECTION 02

Solution-1

  • \[\begin{aligned} &F_{1}=0.2 P_{1}^{2}+40 P_{1}+120=\mathrm{Rs.}~5255.88/\mathrm{hr}. \\ &F_{2}=0.25 P_{2}^{2}+30 P_{2}+150=\mathrm{Rs.}~4958.55/\mathrm{hr} \end{aligned}\]
    The cost of generation
  • Total cost \(=\) Rs. \(10214.43 / \mathrm{hr}\).

  • \[\begin{aligned} F_1 & = \mathrm{Rs.}~5340/\mathrm{hr} \\ F_2 & = \mathrm{Rs.}~4875/\mathrm{hr} \end{aligned}\]
    If the load on each unit is 90 MW, the cost of generation will be
  • Total cost = Rs. 10215/hr

  • Saving will be = Rs. 0.57/hr.

SECTION 03

Problem-2

\[\begin{aligned} \dfrac{dF_1}{dP_1} & = 0.1P_1+3.0~\mathrm{Rs./MWhr} \end{aligned}\]
image
Determine the incremental cost of received power and the penalty factor of the plant shown in Fig., if the incremental cost of production is
SECTION 04

Solution-2

\[\begin{aligned} \dfrac{dF_1}{dP_1} & = 0.1P_1+3.0~\mathrm{Rs./MWhr} \end{aligned}\]
SECTION 05

Problem-3

A two-bus system is shown in Fig. If a load of 125 MW is transmitted from plant 1 to the load, a loss of 15.625 MW is incurred. Determine the generation schedule and the load demand if the cost of received power is Rs. 24/MWhr. Solve the problem using coordination equations and the penalty factor method approach. The incremental production costs of the plants are

image
\[\begin{aligned} \dfrac{dF_1}{dP_1} & = 0.025P_1+15 \\ \dfrac{dF_2}{dP_2} & = 0.05P_2+20 \end{aligned}\]
SECTION 06

Solution-3

\[\begin{aligned} \dfrac{dF_1}{dP_1} & = 0.025P_1+15 \\ \dfrac{dF_2}{dP_2} & = 0.05P_2+20 \end{aligned}\]
image
  • \[\begin{aligned} & 0.025 P_{1}+15+\lambda 0.002 P_{1}=\lambda \\ \Rightarrow & 0.025 P_{1}+0.048 P_{1}+15=24 \\ \Rightarrow & 0.073 P_{1}=9 \\ \Rightarrow & P_{1}=123.28 \mathrm{MW} \end{aligned}\]
    Substituting in the coordination equation for plant
  • \[\begin{gathered} 0.05 P_{2}+20=24 \\ \Rightarrow P_{2}=80 \mathrm{MW} . \end{gathered}\]
    The coordination equation for plant 2,
  • Transmission loss \(P_{L}=0.001 \times(123.28)^{2}=15.19 \mathrm{MW}\)

  • Load, \(P_{D}=123.28+80-15.19=188.1 \mathrm{MW}\).

  • \[\begin{aligned} & \frac{1}{1-\frac{\partial P_{L}}{d P_{1}}}=\frac{1}{1-\left(0.002 P_{1}\right)} \\ & \frac{d F_{1}}{d P_{1}}\left(\frac{1}{1-0.002 P_{1}}\right)=24 \\ \Rightarrow & \frac{0.025 P_{1}+15}{1-0.002 P_{1}}=24 \\ \therefore & P_{1}=123.28 \mathrm{MW} \end{aligned}\]
    Penalty factor of Plant-1 is
  • Since \(\dfrac{dP_L}{dP_2}=0 \Rightarrow L_2 = \text{unity}\)

  • \[\begin{aligned} 0.05P_2+20& = 24\\ \Rightarrow P_2 & = 80~\mathrm{MW} \end{aligned}\]
    The incremental cost of received power equals the incremental cost of production
SECTION 07

Problem-4

Two generating stations A and B have full load capacities of 200 MW and 75 MW respectively. The inter-connector connecting the two stations has an induction motor/synchronous generator (plant C) of full load capacity 25 MW. Percentage changes of speeds of A, B and C are 5, 4 and 3 respectively. The loads on bus bars A and B are 75 MW and 30 MW respectively. Determine the load taken by the set C and indicate the direction in which the energy is flowing.

image
SECTION 08

Solution-4

Given data:

  • F.L. MW 200, 75, 25

  • % speed change 5, 4, & 3

  • Loads 75 MW and 30 MW

image
  • \[\begin{aligned} & \dfrac{5}{200}(75+x)+\dfrac{3x}{25} = \dfrac{4}{75}(30-x) \\ & \Rightarrow x = -1.35~\mathrm{MW} \end{aligned}\]
    The total reduction in frequency from both A and C and the reduction of frequency from B when referred to Bus-B should be same
  • Hence, 1.35 MW of power will flow from B to A

SECTION 09

Problem-5

Two turbo-alternators rated for 110 MW and 210 MW have governor drop characteristics of 5 per cent from no load to full load. They are connected in parallel to share a load of 250 MW. Determine the load shared by each machine assuming free governor action.

SECTION 10

Solution-5